47. At the end of each adjudication proceeding pursuant to this Order, the adjudicator and each party to the contract participating in the proceedings must report on the adjudication by answering the questions in the form in Schedule 2.
The adjudicator and the parties to the contract are to send the duly completed form to the secretariat of the Conseil du trésor. The secretariat is to send a copy of the form completed by the adjudicator to the Institut de médiation et d’arbitrage du Québec and a copy of the form completed by each enterprise to the Coalition Against Payment Delays in the Construction Industry.
M.O. 2018-01, s. 47.
In force: 2018-08-02
47. At the end of each adjudication proceeding pursuant to this Order, the adjudicator and each party to the contract participating in the proceedings must report on the adjudication by answering the questions in the form in Schedule 2.
The adjudicator and the parties to the contract are to send the duly completed form to the secretariat of the Conseil du trésor. The secretariat is to send a copy of the form completed by the adjudicator to the Institut de médiation et d’arbitrage du Québec and a copy of the form completed by each enterprise to the Coalition Against Payment Delays in the Construction Industry.